AfDB aprueba proyectos del sector eléctrico por valor de 210 millones de dólares en Nigeria

Fecha: 28/11/2019

 

Fuente: Energy Mix Report

 

The board of the African Development Bank (AfDB) has approved the Transmission Company of Nigeria’s, TCN’s, NTEP -1 projects in a board resolution in Abidjan.

The NTEP is one of the projects under TREP financed by AfDB that is targeted at rehabilitating and expanding parts of the transmission grid in the North West, South South and the South East.

The project would reconstruct old transmission lines and build new ones as well as construct new substations, contributing to further increase in TCN’s transmission capacity.

In a statement made available to Vanguard by the General Manager (Public Affairs), Ndidi Mbah, it stated that, even though the approval has just been given, the company had already concluded environmental studies including resettlement action plan in which people that would be affected by the acquisition of the Right of Way (RoW) for the proposed transmission lines were identified, the report had been submitted to AfDB.

“The advert for the pre-qualification of contractors had been carried out under advance procurement and evaluation of submissions from consultants that submitted “Expression of interest” for the procurement of consultancy for the project is on-going.

“Adopting the use of advance procurement in the execution of its projects, which has given TCN lead time, reducing procurement period by 6months.

“The procurement processes for the project is about 70 percent completed, meaning that execution of the projects under NTEP-1 would soon commence in earnest, even though it has just been approved by the AfDB board.

TCN further noted that the NTEP-1 projects would address some transmission lines and substations requirements in the North West, South South and South East regions of the nation.

“In the North West, the projects that would be executed include the construction of 212KM Double Circuit 330kV Quad conductor (Kaduna to Kano); installation of 2x150MVA and 2x60MVA transformers and bay extensions in Zara.

“Installation of 2x150MVA and 2x60MVA transformers with associated bay feeders and bay extensions in Kaduna Millennium city; installation of 2x60MVA transformers and outgoing feeders in Rigasa Kaduna; and the installation of 2x60MVA transformers and out-going feeders in jaji, Kaduna.

“The substations would all have turned in and turn out transmission lines.

In the South South and Sourh East, NTEP-1 would reconstruct the 107KM double circuit Delta-Benin transmission lines into a 330kV quad line; reconstruct the 138KM Alaoji- Ihiala – Onitsha Single Circuit line into 330kV Double Circuit Quad line. “

TCN also noted that NTEP-2 which would execute projects mainly in the North East and parts of the central states of the nation is also in the pipeline and has reached advanced stage on the funding processing.

Otras Noticias
Seguimiento de las operaciones de importación y exportación entre Tánger Med y la Bahía de Algeciras

  Fuente: Éco Actu   Dans le contexte actuel de pandémie mondiale, les deux autorités portuaires de Tanger Med et Baie d’Algésiras, poursuivent leurs ac...

$ 450 millones más para la inclusión digital y financiera en Marruecos

FUENTE: INFO MÉDIAIRE El Banco Mundial acaba de aprobar un préstamo de 450 millones de dólares para apoyar el impulso de las reformas emprendidas por Marruec...

Cadenas de valor mundiales. Marruecos refuerza su posición

Fuente: leseco.ma En l’espace de 13 ans, le Maroc a gagné 7,6% dans sa participation dans les chaînes de valeur mondiales pour s’établir à 46,7% en 2018...

La UE invertirá 2,7 billones de SHS en Uganda

  Fuente: The Observer   The European Union (EU) is set to invest some Shs 2.7 trillion (about €646 million) in Uganda in the next five years. This was reve...